Turn a house footprint and roof pitch into squares, shingle bundles and a full order list.
- Roof area
- 1,503 ft²
- Underlayment
- 2 rolls
- Ridge cap
- 2 bundles
At 6:12 the slope adds 11.8% to the footprint, so measuring the ground plan alone would come up 159 ft² short.
Products and waste
The roof, end and plan
Drag the peak to change the pitchA gable roof at 6:12, 26.6°. Each rafter runs 17.9 ft over 16 ft of level run and rises 8 ft. The ridge runs 42 ft.
Working
- 1Footprint with the overhang on every side42 ft × 32 ft = 1,344 ft²
- 2Slope factor for this pitch√(1 + (612)²) = 1.118
- 3Roof area: footprint times the slope factor1,344 × 1.118 = 1,502.6 ft²
- 4Squares, then the waste allowance1,502.6100× (1 + 10%) = 16.529 squares
- 5Whole bundles: round up16.529 × 3 = 49.59, so 50 bundles
- 6Check: the bundles cover the roof and its allowance50 bundles cover 1,666.7 ft², at least 16.529 squares
What to order
| Item | Quantity | Basis |
|---|---|---|
| Shingle bundles3 to a square | 50 | 3 to a square |
| Synthetic underlayment10 squares a roll | 2 rolls | 10 squares a roll |
| Or #15 felt4 squares a roll | 5 rolls | 4 squares a roll |
| Ridge cap bundles42 ft of ridge and hips | 2 | 42 ft of ridge and hips |
| Starter strip, eavesAlong every eave | 84 ft | Along every eave |
| Drip edgeEaves plus 71.6 ft of rakes | 155.6 ft | Eaves plus 71.6 ft of rakes |
From the IRC section on asphalt shingles, R905.2, as printed by the City of Hopkins, MN. Your local code and the shingle maker’s instructions decide; ask your building department.
The same roof at other pitches
| Pitch | Angle | Area | Bundles | Shingle rule |
|---|---|---|---|---|
| 2:129.5°, factor 1.014 | 9.5° | 1,363 ft² | 45double underlayment | 2:12 to under 4:12: double underlayment |
| 3:1214°, factor 1.031 | 14° | 1,385 ft² | 46double underlayment | 2:12 to under 4:12: double underlayment |
| 4:1218.4°, factor 1.054 | 18.4° | 1,417 ft² | 47one layer | 4:12 and up: one layer |
| 5:1222.6°, factor 1.083 | 22.6° | 1,456 ft² | 49one layer | 4:12 and up: one layer |
| 6:12 (yours)26.6°, factor 1.118 | 26.6° | 1,503 ft² | 50one layer | 4:12 and up: one layer |
| 7:1230.3°, factor 1.158 | 30.3° | 1,556 ft² | 52one layer | 4:12 and up: one layer |
| 8:1233.7°, factor 1.202 | 33.7° | 1,615 ft² | 54one layer | 4:12 and up: one layer |
| 9:1236.9°, factor 1.25 | 36.9° | 1,680 ft² | 56one layer | 4:12 and up: one layer |
| 10:1239.8°, factor 1.302 | 39.8° | 1,749 ft² | 58one layer | 4:12 and up: one layer |
| 12:1245°, factor 1.414 | 45° | 1,901 ft² | 63one layer | 4:12 and up: one layer |
How it's worked out
Pitch is the rise in inches for every 12 inches of level run, written 6:12 or "6 in 12". A sloped roof is larger than the ground it covers, so the footprint is multiplied by a slope factor, the length of roof over one foot of run.
At 6:12 the factor is 1.118 and at 12:12 it is 1.414, the same as the correction factors in Owens Corning’s roofing guide. The footprint here includes the overhang on every side, because shingles cover the eaves and rakes too.
Roofing is sold by the square, 100 square feet of roof. Owens Corning packs most laminate shingles three bundles to a square and suggests adding 10 to 15% for cuts. The tool adds your waste figure w, multiplies by b bundles to a square, then rounds up to whole bundles.
A hip roof with the same pitch on every face has the same area as a gable on the same footprint. Its ridge is the longer side less the shorter one. Each of its four hips runs from a corner to the ridge; with S the shorter side, overhang included, each one is this long.
The rest of the list follows from the edges. Starter strip runs along every eave and drip edge along the eaves and rakes. Synthetic underlayment comes in rolls of 10 squares and #15 felt in rolls of 4, per Owens Corning. Ridge cap is counted from the ridge and hips at the coverage on your bundle; GAF’s Seal-A-Ridge sheet gives about 100 linear feet for 4 bundles.
Worked examples
Marcus prices a new roof on a 40 by 30 ft ranch
With a foot of overhang all round, the footprint is 42 by 32 ft, 1,344 ft². At 6:12 the roof is 1,503 ft², or 139.6 m², which is 15.03 squares.
With 10% for waste that is 16.53 squares, so at three to a square Marcus should see about 50 bundles on a quote. He also needs 2 rolls of synthetic underlayment, 42 ft of ridge and 155.6 ft of drip edge.
Elena lists materials for a 50 by 32 ft hip roof
Her roof has 18 inches of overhang and a 5:12 pitch, so it covers 2,010 ft². A hip has more cuts than a gable, so she allows 15%, which gives 23.11 squares and 70 bundles.
The four hips add up to 103.2 ft and the ridge to 18 ft, so she needs 5 bundles of ridge cap at 30 ft a bundle. Every edge is an eave, so drip edge and starter strip both run 176 ft. The same house as a gable at 10% waste would take 67 bundles.
Sam checks whether his shed roof can take shingles
Sam’s 12 by 10 ft shed has a single slope at 3:12 and 6 inches of overhang. The roof is 147 ft², and with 10% waste that is 5 bundles.
3:12 is above the 2:12 floor for asphalt shingles, but under 4:12, so the IRC rule printed by the City of Hopkins calls for double underlayment. That makes 2 rolls of synthetic rather than 1. Drip edge runs 35.7 ft: the low eave and both sloping sides.
Reading your result
Pitch changes the bundle count more than people expect. Marcus’s ranch takes 47 bundles at 4:12, 50 at 6:12 and 63 at 12:12, on the same footprint. The pitch table shows the steps in between.
The overhang counts. Leave it out and Marcus’s roof drops from 1,503 ft² to 1,342 ft², and the bundles from 50 to 45.
The pitch bands are a code minimum, not a recommendation. Below 2:12, asphalt shingles are not allowed; from 2:12 up to 4:12 they need two layers of underlayment. Your local code and the shingle maker’s instructions decide. Ask your building department before you buy.
This is a materials estimate for ordering and for checking a quote, not a roof design or a code review. It does not count valleys, dormers, flashing, vents or fasteners.
Common mistakes
Measuring the floor plan instead of the roof. Inside walls are smaller than the roof by the wall thickness and the overhang. Measure the outside of the walls, then add the overhang.
Using the footprint as the roof area. At 6:12 the slope adds 11.8% to Marcus’s footprint, 159 ft² he would be short.
Assuming every product is three bundles a square. Owens Corning gives three for typical laminate shingles, but not every product is packed that way. The figure printed on the wrapper is the one to use.
Treating a hip roof as more roof. On the same footprint and pitch the area is the same; what grows is the waste from angled cuts and the length of cap for the hips.