MoneyFinancial Math

Economic Order Quantity
calculator.

Find the cheapest order size, when to reorder, and if a price break pays.

Before you rely on this result.This is an estimate for planning. Banks, lenders and other providers apply their own rules, fees and rounding, so confirm figures with them before you commit to a financial decision. Sources used on this page.

How it's worked out

Two costs pull in opposite directions. Each order has a fixed cost: the time to raise it, freight, receiving and checking. Big orders spread that cost thinly. But big orders also leave more stock on the shelf, and stock costs money to hold: the cash tied up, the space, insurance, damage and items going out of date. The best order size is where the two are balanced.

Q∗\displaystyle Q^{*}=2DSH\displaystyle {}= \sqrt{\dfrac{2DS}{H}}cost a year\displaystyle \text{cost a year}=DQS+Q2H\displaystyle {}= \dfrac{D}{Q}\,S + \dfrac{Q}{2}\,H
  • D is how many units you use or sell in a year.
  • S is the cost of placing and receiving one order, whatever its size.
  • H is the cost of holding one unit for a year. Buyers often set it as a share of the unit cost, such as 20% of a $25 item = $5.
  • Q is the order size. On average half an order sits on the shelf, which is why holding cost uses Q over 2.

Ford W. Harris published this formula in 1913. At the answer, the yearly ordering cost and the yearly holding cost are exactly equal, which is a quick check on any result.

The reorder point tells you when to order. It is the demand you expect during the lead time plus a safety stock for busy spells.

reorder point\displaystyle \text{reorder point}=d×L+z×σ×L\displaystyle {}= d \times L + z \times \sigma \times \sqrt{L}

Here d is demand a day, L the lead time in days, σ the standard deviation of daily demand and z the value from the normal curve for your service level (1.645 for 95%). The tool assumes each day's demand is independent and the lead time is fixed.

Worked examples

Dana's bike shop helmets

Dana sells about 1,200 helmets a year. An order costs her $50 to place, ship and check in, and holding a $25 helmet for a year costs 20% of its price, or $5. The best order is 154.9, so 155 helmets, about 7.7 times a year, one order every 47.1 days.

She sells 3.3 a day and waits 7 days for a delivery. With a spread of 2 a day and a 95% service level, she needs 8.7 helmets of safety stock, so she reorders at 23 + 8.7 = 31.7. Open this example in the tool

Out of habit she orders 400 at a time. That costs $1,150.00 a year to order and hold, $375 more than the best size. But her supplier offers $24 a helmet on orders of 400 or more. Counting the helmets themselves, the offer comes to $29,910 a year against $30,775, a saving of $865. The 400 only pays because of the discount: it breaks even at $24.70 a helmet.

A distributor on a working-day year

A distributor ships 8,000 units a year of a $16 item over 250 working days. Orders cost $120 each and holding runs at 25% of value, so H is $4. The best order is 693 units, every 21.7 working days. With a 12-day lead time and a daily spread of 10 units, the reorder point is 384 + 57 = 441.

Their old habit of 2,000 units a time costs $4,480 a year against $2,771, which is $1,709 for nothing unless a discount comes with it. Open this example in the tool

A café's coffee beans

A café uses 520 bags of beans a year at $40 a bag, pays $15 shipping per order and counts $12 a bag a year for holding, since beans go stale. Expensive holding pushes the order down to 36 bags, about every 25 days. With a 3-day lead time and a 98% service level, the reorder point is 7.1 bags. Open this example in the tool

Reading your result

Do not chase the exact figure. The cost curve is flat near the bottom. Ordering 25% more than the best size adds only 2.5% to the yearly cost, and even half or double the best size adds 25% and 25%. So round to a full case, a pallet or the supplier's minimum.

The answer moves with the square root of its inputs. Doubling demand raises the best order by about 41%, not 100%. That is why a rough holding rate is good enough: a guess of 20% instead of 25% shifts the answer by about 12%.

The service level is the share of order cycles that end without running out. At 95%, about 1 cycle in 20 dips into a stockout. Going from 95% to 99% raises z from 1.645 to 2.326, so the safety stock grows by about 41%. Save the high levels for items where running out is costly, such as a part that stops a machine.

When your lead time is longer than the time between orders, an order is always in transit. Compare the reorder point with what is on the shelf plus what is on order, or you will order twice.

Common mistakes

  • Counting the goods in the order cost. S is only the cost of the order itself. The price of the units belongs in the unit cost.
  • Using storage rent alone as the holding cost. The cash tied up in stock is often the largest part. Add insurance, damage and the risk of items going out of date.
  • Mixing time periods. Demand and holding cost must both be yearly. A monthly holding rate of 2% is 24% a year.
  • Ignoring a price break. A discount on bigger orders can beat the best size by a wide margin, as Dana's helmets show. Check it in the price break card.
  • Setting the service level to 99.9% for everything. Safety stock climbs steeply near 100%, and slow movers end up with months of spare stock.

Questions people ask

It depends on your cost of capital, storage, insurance, shrinkage and how quickly the item becomes obsolete, so estimate it for your own business: add up a year of those costs and divide by the average value of inventory held. Perishable or fast-changing products have much higher rates than durable, slow-moving ones.

Sources